Case Study – Distillery Segment Boiler Automation & Electrical Systems 25 TPH Cogeneration Boiler
- Feb 12
- 2 min read
Updated: 2 days ago

Project Overview
End User: Ashoka Distillers & Chemicals Pvt.Ltd.
Project: 25 TPH Cogeneration Boiler Automation
Industry Segment: Distillery & Chemical Manufacturing
Location: India
Client / EPC Contractor: M/s Cogent Engineers Pvt. Ltd.
Automation & Electrical Partner: CABISOL

Background & Requirement
Ashoka Distillers & Chemicals Pvt. Ltd. required a highly reliable and energy-efficient automation solution for its 25 TPH boiler, which is a critical utility for continuous distillery operations.
Key requirements included:
Safe and stable boiler operation
Accurate steam, water, air and flue gas control
Energy optimization using VFDs
Centralized monitoring through PLC & HMI
Integration-ready architecture for future expansion
Scope of Work by CABISOL
CABISOL executed the project on a turnkey instrumentation, VFD, and control system basis.
Instrumentation Scope
Pressure, temperature & draft gauges
Thermocouples with thermowells
Flow elements (orifice plates, flow nozzles)
Pressure & DP transmitters
Drum level & deaerator level measurement
Control valves for:
Feed water
Superheater temperature
Deaerator pressure & level
Minimum recirculation

Variable Frequency Drives & Soft Starters
Supplied and engineered ABB VFD & Soft Starter Panels for critical boiler auxiliaries:
ID Fans -150 HP
FD Fans - 270 HP
Boiler Feed Water Pumps - 190 HP with COS
Pocket Feeders & Screw Feeders
Key benefits:
Energy savings
Smooth motor starting
Reduced mechanical stress
Improved process control

Control System Architecture
PLC Platform
ABB AC500 Series
I/O System
ABB S500 Distributed I/O
HMI
ABB CP400 Touch Panels
Programming Software
PS501 (IEC 61131-3 compliant)
Control system covered:
Boiler steam & water circuit
Air & flue gas system
Fan control & interlocks
Alarm, trip & safety logic
Manual / Auto / Remote operation modes

Control Room Engineering
CABISOL also delivered control room layout engineering, ensuring:
Ergonomic operator access
Clear segregation of PLC, VFD, and power panels
Provision for UPS and future expansion
Engineering Highlights
Designed for continuous distillery operation
High reliability for 24×7 boiler service
Energy-efficient fan & pump control
Modular PLC architecture for scalability
Easy maintenance with clear diagnostics
Future-ready communication (Profibus / Modbus / Ethernet)
Project Challenges & Solutions
Challenge | Solution |
High thermal & dusty environment | Industrial-grade instruments & IP-rated panels |
Variable steam demand | VFD-based fan & pump control |
Operational safety | Interlocks, alarms & fail-safe logic |
Limited shutdown window | Pre-engineered panels & structured commissioning |
Results & Benefits to Client
Stable boiler operation
Improved steam quality & control
Reduced power consumption
Enhanced equipment life
Centralized monitoring & diagnostics
Compliance with industrial safety standards
Conclusion
The successful execution of the 25 TPH Boiler Automation Project at Ashoka Distillers & Chemicals Pvt. Ltd. demonstrates CABISOL's strong capability in delivering integrated automation solutions for the distillery sector.
This project stands as a reference installation for:
Distilleries
Ethanol plants
Cogeneration utilities
Process & utility automation